Staff Report #8 – Financial Update – Capital Budget Programs – May 31, 2022

Staff Report #8

June 29, 2022

To All Commissioners

Re: Financial Update – Capital Budget Programs – May 31, 2022

Recommendation

That the report be NOTED and FILED.

Background

Summarized in the table below is the 2022 Capital Program Summary for the five-month period ending May 31, 2022.

Summary of 2021 Capital Budget Program Activity

Five Months Ending May 31, 2022

Description  Actual  Budget  Amount Under Budget (Over Budget)
Program
Bus replacement $ 404,201  $ 11,583,900  $ 11,179,699
Bus expansion 113,721 3,335,000 3,221,279
Facility upgrades 19,148 603,000 583,852
Fare processing equipment 2,495,000 2,495,000
Information systems & hardware 98,266 730,000 631,734
Shop & garage equipment 56,171 200,000 143,829
Service fleet replacement 50,000 50,000
Stop upgrades 866,900 866,900
Bus stop amenities 194,616 1,045,000 850,384
Fleet radio replacement 625,000 625,000
Smart card program 505,000 505,000
TMP 2030 – BRT Strategy 1,500,000 1,500,000
Total $ 886,123  $ 23,538,800  $ 22,652,677
Funding
Provincial Gas Tax $ – $ 7,388,600  $ 7,388,600
Capital Program Reserve 154,437 1,846,900 1,692,463
City – Development Charges 12,129 355,700 343,571
City of London 493,445 7,869,700 7,376,255
City – Federal Gas Tax 2,866,000 2,866,000
ICIP – Provincial 102,777 1,459,900 1,357,123
ICIP – Federal 123,335 1,752,000 1,628,665
Total $ 886,123  $ 23,538,800  $ 22,652,677

The following programs are underway through the first five months of the year, with narrative focusing on the year-to-date progress.

Bus replacement – Some of the peripheral equipment (cameras, fareboxes, etc.) has started to arrive in anticipation of the receipt of replacement and expansion buses.

Facility upgrades – projects underway at Highbury facility including painting and gate upgrades.

Information systems & hardware – Expenditures incurred to date for the purchasing of workstations and networking equipment.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and equipment.

Bus stop amenities – nearly half of the 60 bus shelters were installed in late 2021 and into the first quarter of 2022. The remaining 30 shelters will be installed upon arrival expected in late 2022.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.