Staff Report #8 – Financial Update – Capital Budget Programs – July 31, 2022

Staff Report #8

August 31, 2022

To All Commissioners

Re: Financial Update – Capital Budget Programs – July 31, 2022

Recommendation

That the report be NOTED and FILED.

Background

Summarized in the table below is the 2022 Capital Program Summary for the seven-month period ending July 31, 2022.

Summary of 2022 Capital Budget Program Activity Seven Months Ending July 31, 2022

Description  Actual  Budget Amount
Under Budget (Over Budget)
Program
Bus replacement $ 503,648  $ 12,361,300  $ 11,857,652
Bus expansion 113,721 3,551,000 3,437,279
Facility upgrades 130,812 603,000 472,188
Fare processing equipment 2,495,000 2,495,000
Information systems & hardware 104,654 730,000 625,346
Shop & garage equipment 78,438 200,000 121,562
Service fleet replacement 40,742 50,000 9,258
Stop upgrades 866,900 866,900
Bus stop amenities 194,616 1,045,000 850,384
Fleet radio replacement 625,000 625,000
Smart card program 505,000 505,000
TMP 2030 – BRT Strategy 1,500,000 1,500,000
Total $ 1,166,631  $ 24,532,200  $ 23,365,569
Funding
Provincial Gas Tax $ – $ 8,166,000  $ 8,166,000
Capital Program Reserve 223,834 1,846,900 1,623,066
City – Development Charges 12,170 380,000 367,830
City of London 704,551 7,904,100 7,199,549
City – Federal Gas Tax 2,866,000 2,866,000
ICIP – Provincial 102,742 1,530,800 1,428,058
ICIP – Federal 123,335 1,838,400 1,715,065
Total $ 1,166,631  $ 24,532,200  $ 23,365,569

The following programs are underway through the first seven months of the year, with narrative focusing on the year-to-date progress.

Bus replacement / expansion – Some of the peripheral equipment (cameras, fareboxes, etc.) have started to arrive in anticipation of the receipt of replacement and expansion buses. At time of writing, two buses have been received with an uncertain shipment schedule from New Flyer for the remaining buses.

Facility upgrades – projects underway at Highbury facility including painting and gate upgrades.

Information systems & hardware – Expenditures incurred to date for the purchasing of workstations and networking equipment.

Service fleet replacement – receipt in June of replacement inspector van.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and equipment.

Bus stop amenities – nearly half of the 60 bus shelters were installed in late 2021 and into the first quarter of 2022. The remaining 30 shelters will be installed upon arrival expected in late 2022 along with bus stop lighting

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager