Staff Report #13
August 30, 2023
To All Commissioners
Re: Financial Update – Capital Budget Programs – July 31, 2023
Recommendation
That the report be NOTED and FILED.
Background
Summarized in the table below is the 2023 Capital Program Summary for the seven-month period ending July 31, 2023.
Summary of 2023 Capital Budget Program Activity Seven Months Ending July 31, 2023
Description | Actual | Budget | Amount Under Budget (Over Budget) |
|
Program | ||||
Bus replacement | $ 326,331 | $ 12,848,300 | $ 12,521,969 | |
Facility upgrades | 230,363 | 751,600 | 521,237 | |
Fare processing equipment | – | 2,495,000 | 2,495,000 | |
Information systems & hardware | 161,664 | 1,054,000 | 893,136 | |
Shop & garage equipment | 90,374 | 200,000 | 109,626 | |
Service fleet replacement | – | 130,000 | 130,000 | |
Stop upgrades | – | 941,100 | 941,100 | |
Bus stop amenities | – | 578,700 | 578,700 | |
Fleet radio replacement | – | 625,000 | 625,000 | |
Smart card program | – | 450,000 | 450,000 | |
Highbury facility rebuild | – | 2,500,000 | 2,500,000 | |
Total | $ 808,731 | $ 22,574,500 | $ 21,765,769 | |
Funding | ||||
Provincial Gas Tax | $ – | $ 7,773,300 | $ 7,773,300 | |
Capital Program Reserve | 252,038 | 2,325,900 | 2,073,862 | |
City of London | 556,693 | 2,815,400 | 2,258,707 | |
City – Federal Gas Tax | – | 7,403,000 | 7,403,000 | |
ICIP – Provincial | – | 1,025,400 | 1,025,400 | |
ICIP – Federal | – | 1,231,500 | 1,231,500 | |
Total | $ 808,731 | $ 22,574,500 | $ 21,765,769 |
The following programs are underway through the first seven months of the year, with narrative focusing on the year-to-date progress.
Bus replacement – Some of the peripheral equipment (cameras, AVL) has started to arrive in anticipation of the receipt of replacement buses.
Facility upgrades – Expenditures incurred to date for hoist repairs, lighting, security cameras and drainage work.
Information systems & hardware – Expenditures incurred to date for the purchase of workstations and networking equipment.
Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and equipment.
Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.
Recommended by:
Mike Gregor, Director of Finance
Concurred in by:
Kelly S. Paleczny, General Manager