Summarized in the table below is the 2018 Capital Program Summary for the five month period ending May 31, 2018.

Summary of 2018 Capital Budget Program Activity

Five Months Ending May 31, 2018

 Amount
 Under Budget
Description  Actual  Budget  (Over Budget)
Program
Stop Upgrades $ 21,278  $ 110,000  $ 88,722
Service Fleet 33,971 40,000 6,029
Shop Equipment 32,043 200,000 167,957
Software and Hardware 109,216 600,000 490,784
Facility Upgrades 76,227 300,000 223,773
Bus Replacement (8) 4,560,800 4,560,800
Bus Expansion (4) 202,305 2,378,400 2,176,095
Fleet Radio Replacement 625,000 625,000
TMP 2030 – BRT Strategy 1,500,000 1,500,000
Fare Processing Equipment 1,495,000 1,495,000
Smart Card Program 605,000 605,000
Total $ 475,040  $ 12,414,200  $ 11,939,160
Funding
Provincial Gas Tax $ 63,225 $ 5,502,200  $ 5,448,975
Capital Program Reserve 143,283 627,000 483,717
City of London 278,532 4,785,000 4,506,468
Federal Gas Tax 1,500,000 1,500,000
Total $ 253,930  $ 12,414,200  $ 11,939,160

The following programs are underway through the first five months of the year, with narrative focusing on the YTD progress.

Stop Upgrades

The costs incurred to-date are attributable to the remaining expenditures from the 2017 shelter installs. As outlined in Staff Report #2, dated April 25, 2018, an additional $73,000 was requested and approved to carry out the planned 2018 shelter program (10 shelters). The remaining $89,000 in the budget will enable the purchase and installation of these 10 shelters. Shelters have been ordered and the contract for the required cement pads has been awarded. Work began on cement pads on June 25, 2018 for completion by August 30, 2018; with shelters being installed by late September/early October.

Service Fleet

The costs incurred to-date are attributable to the purchase of a new service van. Outstanding expenditures are related to the lighting kits and ancillary equipment required for the van. See Staff Report #8, dated April 25, 2018.

Shop Equipment

Expenditures incurred to-date relate to the ongoing monthly purchase of shop tools. This budget is utilized throughout the year as equipment and tools are required.

Software and Hardware

The costs incurred to-date are attributable to the replacement of the Specialized scheduling system and other workstation and networking equipment replacements. Work on these projects is scheduled to continue for the remainder of the year.

Facility Upgrades

Expenditures incurred to-date relate to the purchase of high speed doors for the fuel service lanes as well as repairs to the maintenance inspection pit. The remaining projects scheduled for 2018, as discussed in Staff Report #8, dated April 25, 2018 include repairs to curbing and parking lot asphalt, reinforcement of columns in A and B bard, grating to be replaced in B barn and new office construction in Human Resources.

Bus Purchases

The costs incurred to-date are attributable to the early purchase of ancillary equipment required for the 2018 bus expansion and replacement projects. Staff Report #8, dated April 25, 2018 discusses the timing and issues related to these programs.

The remaining programs are scheduled to commence in the remainder of 2018. Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager