Staff Report #10 – Financial Update – Capital Budget Programs – October 31, 2021

Staff Report #10

November 24, 2021

To All Commissioners

Re: Financial Update – Capital Budget Programs – October 31, 2021

Recommendation

That the report be NOTED and FILED.

Background

Summarized in the table below is the 2021 Capital Program Summary for the ten-month period ending October 31, 2021.

Summary of 2021 Capital Budget Program Activity Ten Months Ending October 31, 2021

Description  Actual  Budget Amount
Under Budget (Over Budget)
Program
Stop Upgrades $ –  $ 743,700  $ 743,700
Service Fleet 36,198 50,000 13,802
Shop Equipment 60,551 200,000 139,449
Software and Hardware 194,736 680,000 485,264
Facility Upgrades 246,727 500,000 253,273
Bus Replacements 10,325,747 10,619,900 294,153
Bus Expansion 1,263,633 1,300,400 36,767
Bus Stop Amenities 58,512 1,100,000 1,041,488
Fleet Radio Replacement 625,000 625,000
TMP 2030 – BRT Strategy 1,500,000 1,500,000
Fare Processing Equipment 2,495,000 2,495,000
Smart Card Program 22,288 295,000 272,712
Total $ 12,208,392  $ 20,109,000  $ 7,900,608
Funding
Provincial Gas Tax $ 2,278,833 $ 6,615,700  $ 4,336,867
Capital Program Reserve 291,486 1,463,700 1,172,214
City of London 5,802,561 7,403,400 1,600,839
Federal – ICIP 528,858 960,200 431,342
Provincial – ICIP 440,653 800,000 359,347
Federal Gas Tax 2,866,000 2,866,000
Total $ 12,208,392  $ 20,109,000  $ 7,900,608

The following programs are underway through the first ten months of the year, with narrative focusing on the year-to-date progress.

Service Fleet – The replacement vehicle for the Inspector fleet was purchased and has been fully outfitted and placed into service.

Shop Equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and equipment.

Software and Hardware – Expenditures incurred to date for the purchasing of workstations and networking equipment as well as upgrades to the Kronos timekeeping system in Fleet and Facilities.

Facility Upgrades – Expenditures incurred to date for the replacement of doors in C-Barn, upgrades to the lighting at Wonderland, upgrades to the fueling system, as well as siding and concrete repairs at Highbury.

Bus Replacement & Expansion – Expenditures incurred to date for all 19 buses shipped and received as well as the ancillary equipment required for outfitting. A few costs remain outstanding relating to additional ancillary equipment.

Bus Stop Amenities – Expenditures incurred to date for the concrete pads required for the additional shelters to be installed in 2021 as part of the ICIP funded project.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.