Summarized in the table below is the 2023 Capital Program Summary for the nine-month period ending September 30, 2023.

Summary of 2023 Capital Budget Program Activity Nine Months Ending September 30, 2023

Description  Actual  Budget Amount
Under Budget
(Over Budget)
Program
Bus replacement $ 381,230  $ 12,848,300  $ 12,467,070
Facility upgrades 340,519 751,600 411,082
Fare processing equipment 2,495,000 2,495,000
Information systems & hardware 192,985 1,054,000 861,815
Shop & garage equipment 101,296 200,000 98,704
Service fleet replacement 130,000 130,000
Stop upgrades 37,651 941,100 903,449
Bus stop amenities 354,125 578,700 224,575
Fleet radio replacement 625,000 625,000
Smart card program 450,000 450,000
Highbury facility rebuild 2,500,000 2,500,000
Total $ 1,407,805  $ 22,574,500  $ 21,166,695
Funding
Provincial Gas Tax $ – $ 7,773,300  $ 7,773,300
Capital Program Reserve 331,932 2,325,900 1,993,968
City of London 816,300 2,815,400 1,999,100
City – Federal Gas Tax 7,403,000 7,403,000
ICIP – Provincial 117,924 1,025,400 907,476
ICIP – Federal 141,650 1,231,500 1,089,850
Total $ 1,407,805  $ 22,574,500  $ 21,166,695

The following programs are underway through the first nine months of the year, with narrative focusing on the year-to-date progress.

Bus replacement – Some of the peripheral equipment (cameras, AVL) has started to arrive in anticipation of the receipt of replacement buses beginning in December.

Facility upgrades – Expenditures incurred to date for hoist repairs, lighting, security cameras, painting, interior renovations, and drainage work.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and equipment.

For further details on the above projects whose responsibility fall within Fleet & Facilities, please refer to Staff Report #4, dated October 25, 2023.

Information systems & hardware – Expenditures incurred to date for the purchase of workstations and networking equipment.

Stop upgrades – Expenditures incurred to date relate to pouring of bus stop pads.

Bus stop amenities – Expenditures incurred to date relate to the purchase of bus stop lighting.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager