Staff Report #11 – Financial Update – Capital Budget Programs – April 30, 2024

Staff Report #11

May 29, 2024

To All Commissioners

Re: Financial Update – Capital Budget Programs – April 30, 2024

Recommendation

That the report be NOTED and FILED.

Background

Summarized in the table below is the 2024 Capital Program Summary for the four-month period ending April 30, 2024.

Summary of 2024 Capital Budget Program Activity Four Months Ending April 30, 2024

Description  Actual  Budget Amount Under
Budget (Over Budget)
Program
Bus replacement (2023)  $ 12,144,788  $ 12,177,800  $ 33,012
Bus replacement (2024) 14,918,300 14,918,300
Bus expansion 1,848,293 8,495,000 6,646,707
Facility upgrades 22,274 801,800 779,526
Fare processing equipment 2,495,000 2,495,000
Information systems & hardware 62,372 1,188,000 1,125,628
Shop & garage equipment 73,907 240,000 166,093
Service fleet replacement 137,780 155,000 17,220
Stop upgrades 100,000 100,000
Bus stop amenities 224,600 224,600
Fleet radio replacement 625,000 625,000
Smart card program 291,259 408,000 116,741
Highbury facility rebuild 2,500,000 2,500,000
Zero emission bus pilot 25,960,000 25,960,000
Total $ 14,580,673  $ 70,288,500  $ 55,707,827
Funding
Provincial Gas Tax $ 5,521,547 $ 7,731,300  $ 2,209,753
Capital Program Reserve 274,059 1,683,000 1,408,941
City of London 697,776 28,937,700 28,239,924
City – Federal Gas Tax 6,732,500 10,732,500 4,000,000
ICIP – Provincial 615,474 3,736,200 3,120,726
ICIP – Federal 739,317 4,487,800 3,748,483
Senior Government 12,980,000 12,980,000
Total $ 14,580,673 $ 70,288,500  $ 55,707,827

The following programs are underway through the first four months of the year, with narrative focusing on the year-to-date progress.

Bus replacement (2023) – All of the buses have arrived and are now in service.

Bus expansion – All 10 expansion buses have arrived on property and are currently being outfitted for service. Note the expenditures above only include one bus as the remaining nine were received in May.

Facility upgrades – The facility upgrade program is just slightly underway with costs incurred to date pertaining to camera installation at both facilities. The bulk of the sub-projects within the program will continue in the second quarter, including stairs to the body shop roof and door replacements at Wonderland.

Information systems & hardware – Expenditures incurred to date for the purchase of workstations and networking equipment.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and miscellaneous equipment (parts washer).

Service fleet replacement – Expenditures incurred to date relate to the purchase of a new Inspector van, along with a mobile mechanic’s van. The Inspector van is now in service, while the mobile is currently being outfitted for service.

Smart card program – Expenditures incurred to date relate to the handheld project that is currently in progress for the Specialized Service.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager