Staff Report #13 – Financial Update – Capital Budget Programs – March 31, 2024

Staff Report #13

April 24, 2024

To All Commissioners

Re: Financial Update – Capital Budget Programs – March 31, 2024

Recommendation

That the report be NOTED and FILED.

Background

Summarized in the table below is the 2024 Capital Program Summary for the three-month period ending March 31, 2024.

Summary of 2024 Capital Budget Program Activity Three Months Ending March 31, 2024

Description  Actual  Budget  Amount
Under Budget (Over Budget)
Program
Bus replacement (2023)  $ 12,144,788  $ 12,177,800  $ 33,012
Bus replacement (2024) 14,918,300 14,918,300
Bus expansion 1,514,509 8,495,000 6,980,491
Facility upgrades 15,434 801,800 786,366
Fare processing equipment 2,495,000 2,495,000
Information systems & hardware 32,584 1,188,000 1,155,416
Shop & garage equipment 58,052 240,000 181,948
Service fleet replacement 62,958 155,000 92,042
Stop upgrades 100,000 100,000
Bus stop amenities 224,600 224,600
Fleet radio replacement 625,000 625,000
Smart card program 291,259 408,000 116,741
Highbury facility rebuild 2,500,000 2,500,000
Zero emission bus pilot 25,960,000 25,960,000
Total $ 14,119,584  $ 70,288,500  $ 56,168,916
Funding
Provincial Gas Tax $ 5,521,546 $ 7,731,300  $ 2,209,754
Capital Program Reserve 153,595 1,683,000 1,529,405
City of London 601,814 28,937,700 28,335,886
City – Federal Gas Tax 6,732,500 10,732,500 4,000,000
ICIP – Provincial 503,325 3,736,200 3,231,875
ICIP – Federal 604,804 4,487,800 3,881,996
Senior Government 12,980,000 12,980,000
Total $ 14,119,584 $ 70,288,500  $ 56,168,916

The following programs are underway through the first three months of the year, with narrative focusing on the year-to-date progress.

Bus replacement (2023) – All of the buses have arrived on property with 12 of the 15 outfitted and on road. Note the project is a carry forward from 2023 with the ancillary equipment having arrived last year, with only inspection costs outstanding.

Bus expansion – The order of 10 expansion buses is online with the first bus having arrived on property. The remaining buses will be delivered in the second quarter and will be outfitted for service.

Facility upgrades – The facility upgrade program is just slightly underway with costs incurred to date pertaining to camera installation at both facilities. The bulk of the sub-projects within the program will commence in the second quarter, including stairs to the body shop roof and door replacements at Wonderland.

Information systems & hardware – Expenditures incurred to date for the purchase of workstations and networking equipment.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and miscellaneous equipment (parts washer).

Service fleet replacement – Expenditures incurred to date relate to the purchase of a new Inspector van, including applicable lights and decals. A replacement for the mobile van has also been ordered, with delivery expected in the coming weeks. Work will commence immediately to outfit the vehicle for service.

Smart card program – Expenditures incurred to date relate to the handheld project that is currently in progress.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager