Summarized in the table below is the 2024 Capital Program Summary for the seven-month period ending July 31, 2024.

Summary of 2024 Capital Budget Program Activity Seven Months Ending July 31, 2024

Description  Actual  Budget Amount Under Budget (Over Budget)
Program
Bus replacement (2023)  $ 12,454,203  $ 12,177,800  $ (276,403)
Bus replacement (2024) 174,929 14,918,300 14,743,371
Bus expansion 8,992,537 8,495,000 (497,513)
Facility upgrades 204,287 801,800 597,513
Fare processing equipment 2,495,000 2,495,000
Information systems & hardware 305,516 1,188,000 862,484
Shop & garage equipment 119,186 240,000 120,814
Service fleet replacement 144,524 155,000 10,476
Stop upgrades 100,000 100,000
Bus stop amenities 224,600 224,600
Fleet radio replacement 625,000 625,000
Smart card program 291,260 408,000 116,740
Highbury facility rebuild 2,500,000 2,500,000
Zero emission bus pilot 25,960,000 25,960,000
Total $ 22,686,442  $ 70,288,500  $ 47,602,058
Funding
Provincial Gas Tax $ 5,830,961 $ 7,731,300  $ 1,900,339
Capital Program Reserve 569,227 1,683,000 1,113,773
City of London 2,962,261 28,937,700 25,975,439
City – Federal Gas Tax 6,732,500 10,732,500 4,000,000
ICIP – Provincial 2,994,478 3,736,200 741,722
ICIP – Federal 3,597,015 4,487,800 890,785
Senior Government 12,980,000 12,980,000
Total $ 22,686,442 $ 70,288,500  $ 47,602,058

The following programs are underway through the first seven months of the year, with narrative focusing on the year-to-date progress.

Bus replacement (2023) – All of the buses have arrived and are now in service. The unfavourable variance is attributable to a slightly higher bus cost compared to budget.

Bus replacement (2024) – Costs incurred to date relate to the purchase of ancillary equipment in anticipation of the arrival of the 2024 replacement buses, expected in the first quarter of 2025.

Bus expansion – All ten expansion buses have arrived. The unfavourable variance is attributable to a slightly higher net bus cost compared to budget as well as higher than anticipated ancillary equipment (radios, cameras and air filtration system).

Facility upgrades – The facility upgrade program is well underway with costs incurred to date pertaining to camera installations at both facilities, stairs to the body shop roof, door replacements at Wonderland, a large ceiling fan at Wonderland and tent panel replacements at Highbury. The new bus wash for Wonderland approved in May is scheduled for installation in the fourth quarter.

Information systems & hardware – Expenditures incurred to date for the purchase of workstations, networking equipment as well as the Transit Master system upgrade.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and miscellaneous equipment (i.e., parts washer).

Service fleet replacement – Expenditures incurred to date relate to the purchase of a new Inspector van, along with a mobile mechanic’s van. Both units are now in service.

Smart card program – Expenditures incurred to date relate to the handheld project that is currently in progress for the Specialized Service.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager