Background

Summarized in the table below is the 2022 Capital Program Summary for the eight-month period ending August 31, 2022.

Summary of 2022 Capital Budget Program Activity Eight Months Ending August 31, 2022

Description  Actual  Budget  Amount
Under Budget (Over Budget)
Program
Bus replacement $ 3,217,325  $ 12,361,300  $ 9,143,975
Bus expansion 113,721 3,551,000 3,437,279
Facility upgrades 329,774 603,000 273,226
Fare processing equipment 2,495,000 2,495,000
Information systems & hardware 106,687 730,000 623,313
Shop & garage equipment 84,927 200,000 115,073
Service fleet replacement 40,742 50,000 9,258
Stop upgrades 866,900 866,900
Bus stop amenities 283,299 1,045,000 761,701
Fleet radio replacement 625,000 625,000
Smart card program 47,216 505,000 457,784
TMP 2030 – BRT Strategy 1,500,000 1,500,000
Total $ 4,223,691  $ 24,532,200  $ 20,308,509
Funding
Provincial Gas Tax $ 47,216 $ 8,166,000  $ 8,118,786
Capital Program Reserve 232,356 1,846,900 1,614,544
City – Development Charges 12,170 380,000 367,830
City of London 3,640,839 7,904,100 4,263,261
City – Federal Gas Tax 2,866,000 2,866,000
ICIP – Provincial 132,303 1,530,800 1,398,497
ICIP – Federal 158,808 1,838,400 1,679,592
Total $ 4,223,691  $ 24,532,200  $ 20,308,509

The following programs are underway through the first eight months of the year, with narrative focusing on the year-to-date progress.

Bus replacement/expansion – Four of the buses arrived in August and at the time of writing, an additional six have been received in September. Expenditures relate to the four August buses along with peripheral equipment (cameras, fareboxes, etc.) received to date.

Facility upgrades – projects underway at including painting, paving, concrete work and gate upgrades.

Information systems & hardware – Expenditures incurred to date for the purchasing of workstations and networking equipment.

Service fleet replacement – receipt in June of replacement inspector van.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and equipment.

Bus stop amenities – nearly half of the 60 bus shelters were installed in late 2021 and into the first quarter of 2022. The remaining 30 shelters will be installed upon arrival expected in late 2022.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager