Staff Report #7 – Financial Update – Capital Budget Programs – August 31, 2021

Staff Report #7

September 29, 2021

To All Commissioners

Re: Financial Update – Capital Budget Programs – August 31, 2021

Recommendation

That the report be NOTED and FILED.

Background

Summarized in the table below is the 2021 Capital Program Summary for the eight-month period ending August 31, 2021.

Summary of 2021 Capital Budget Program Activity Eight Months Ending August 31, 2021

Description  Actual  Budget Amount Under Budget (Over Budget)
Program
Stop Upgrades $ –  $ 743,700  $ 743,700
Service Fleet 36,198 50,000 13,802
Shop Equipment 49,915 200,000 150,085
Software and Hardware 117,031 680,000 562,969
Facility Upgrades 207,726 500,000 292,274
Bus Replacements 9,098,271 10,619,900 1,521,629
Bus Expansion 1,250,186 1,300,400 50,214
Bus Stop Amenities 54,950 1,100,000 1,045,050
Fleet Radio Replacement 625,000 625,000
TMP 2030 – BRT Strategy 1,500,000 1,500,000
Fare Processing Equipment 2,495,000 2,495,000
Smart Card Program 22,288 295,000 272,712
Total $ 10,836,565  $ 20,109,000  $ 9,272,435
Funding
Provincial Gas Tax $ 1,051,358 $ 6,615,700  $ 5,564,342
Capital Program Reserve 203,144 1,463,700 1,260.556
City of London 5,759,023 7,403,400 1,644,377
Federal – ICIP 522,055 960,200 438,185
Provincial – ICIP 434,986 800,000 365,014
Federal Gas Tax 2,866,000 2,866,000
Total $ 10,836,565  $ 20,109,000  $ 9,272,435

The following programs are underway through the first eight months of the year, with narrative focusing on the year-to-date progress.

Service Fleet – The replacement vehicle for the Inspector fleet was purchased and has been fully outfitted and placed into service.

Shop Equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and equipment.

Software and Hardware – Expenditures incurred to date for the purchasing of workstations and networking equipment as well as upgrades to the Kronos timekeeping system in Fleet and Facilities.

Facility Upgrades – Expenditures incurred to date for the replacement of doors in C-Barn, upgrades to the lighting at Wonderland, upgrades to the fueling system, as well as siding and concrete repairs at Highbury.

Bus Replacement & Expansion – Expenditures incurred to date for 17 buses shipped and received by the end of August as well as the ancillary equipment required for outfitting. The remaining two buses arrived in September with all buses expected to be placed into service by the end of October.

Bus Stop Amenities – Expenditures incurred to date for the concrete pads required for the additional shelters to be installed in 2021 as part of the ICIP funded project.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager