Summarized in the table below is the 2023 Capital Program Summary for the eight-month period ending August 31, 2023.

Summary of 2023 Capital Budget Program Activity Eight Months Ending August 31, 2023

Description  Actual  Budget Amount
Under Budget (Over Budget)
Program
Bus replacement $ 379,785  $ 12,848,300  $ 12,468,515
Facility upgrades 236,102 751,600 515,498
Fare processing equipment 2,495,000 2,495,000
Information systems & hardware 161,664 1,054,000 893,136
Shop & garage equipment 92,759 200,000 107,241
Service fleet replacement 130,000 130,000
Stop upgrades 941,100 941,100
Bus stop amenities 354,125 578,700 224,575
Fleet radio replacement 625,000 625,000
Smart card program 450,000 450,000
Highbury facility rebuild 2,500,000 2,500,000
Total $ 1,224,435  $ 22,574,500  $ 21,350,065
Funding
Provincial Gas Tax $ – $ 7,773,300  $ 7,773,300
Capital Program Reserve 254,423 2,325,900 2,071,477
City of London 710,439 2,815,400 2,104,961
City – Federal Gas Tax 7,403,000 7,403,000
ICIP – Provincial 117,924 1,025,400 907,476
ICIP – Federal 141,650 1,231,500 1,089,850
Total $ 1,224,435  $ 22,574,500  $ 21,350,065

The following programs are underway through the first eight months of the year, with narrative focusing on the year-to-date progress.

Bus replacement – Some of the peripheral equipment (cameras, AVL) has started to arrive in anticipation of the receipt of replacement buses in November.

Facility upgrades – Expenditures incurred to date for hoist repairs, lighting, security cameras and drainage work.

Information systems & hardware – Expenditures incurred to date for the purchase of workstations and networking equipment.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and equipment.

Bus stop amenities – Expenditures incurred to date relate to the purchase of bus stop lighting.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager