Summarized in the table below is the 2024 Capital Program Summary for the five-month period ending May 31, 2024.

Summary of 2024 Capital Budget Program Activity Five Months Ending May 31, 2024

Description  Actual  Budget Amount Under Budget (Over Budget)
Program
Bus replacement (2023)  $ 12,404,036  $ 12,177,800  $ (226,236)
Bus replacement (2024) 14,918,300 14,918,300
Bus expansion 8,939,666 8,495,000 (444,666)
Facility upgrades 27,469 801,800 774,331
Fare processing equipment 2,495,000 2,495,000
Information systems & hardware 201,449 1,188,000 986,551
Shop & garage equipment 82,355 240,000 157,645
Service fleet replacement 142,096 155,000 12,904
Stop upgrades 100,000 100,000
Bus stop amenities 224,600 224,600
Fleet radio replacement 625,000 625,000
Smart card program 291,260 408,000 116,740
Highbury facility rebuild 2,500,000 2,500,000
Zero emission bus pilot 25,960,000 25,960,000
Total $ 22,088,331  $ 70,288,500  $ 48,200,169
Funding
Provincial Gas Tax $ 5,780,794 $ 7,731,300  $ 1,950,506
Capital Program Reserve 425,901 1,683,000 1,257,099
City of London 2,596,397 28,937,700 26,341,303
City – Federal Gas Tax 6,732,500 10,732,500 4,000,000
ICIP – Provincial 2,976,872 3,736,200 759,328
ICIP – Federal 3,575,867 4,487,800 911,933
Senior Government 12,980,000 12,980,000
Total $ 22,088,331 $ 70,288,500  $ 48,200,169

The following programs are underway through the first five months of the year, with narrative focusing on the year-to-date progress.

Bus replacement (2023) – All of the buses have arrived and are now in service. The unfavourable variance is attributable to a slightly higher bus cost compared to budget.

Bus expansion – All 10 expansion buses have arrived on property and are currently being outfitted for service. The unfavourable variance is attributable to a slightly higher net bus cost compared to budget as well as higher than anticipated ancillary equipment (radios, cameras and air filtration system).

Facility upgrades – The facility upgrade program is slightly underway with costs incurred to date pertaining to camera installations at both facilities. A number of projects are either completed or near completion including stairs to the body shop roof, door replacements at Wonderland and a large ceiling fan at Wonderland. The new bus wash for Wonderland approved in May is scheduled for installation in the fourth quarter.

Information systems & hardware – Expenditures incurred to date for the purchase of workstations, networking equipment as well as the Transit Master system upgrade.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and miscellaneous equipment (i.e., parts washer).

Service fleet replacement – Expenditures incurred to date relate to the purchase of a new Inspector van, along with a mobile mechanic’s van. Both units are now in service.

Smart card program – Expenditures incurred to date relate to the handheld project that is currently in progress for the Specialized Service.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager