Staff Report #9 – Financial Update – Capital Budget Programs – October 31, 2023

Staff Report #9

November 29, 2023

To All Commissioners

Re: Financial Update – Capital Budget Programs – October 31, 2023

Recommendation

That the report be NOTED and FILED.

Background

Summarized in the table below is the 2023 Capital Program Summary for the ten-month period ending October 31, 2023.

Summary of 2023 Capital Budget Program Activity Ten Months Ending October 31, 2023

Description  Actual  Budget Amount Under Budget (Over Budget)
Program
Bus replacement $ 381,230  $ 12,848,300  $ 12,467,070
Facility upgrades 340,519 751,600 411,082
Fare processing equipment 2,495,000 2,495,000
Information systems & hardware 352,618 1,054,000 702,182
Shop & garage equipment 105,031 200,000 94,969
Service fleet replacement 59,940 130,000 70,060
Stop upgrades 37,651 941,100 903,449
Bus stop amenities 354,125 578,700 224,575
Fleet radio replacement 625,000 625,000
Smart card program 41,608 450,000 408,392
Highbury facility rebuild 2,500,000 2,500,000
Total $ 1,672,722  $ 22,574,500  $ 20,901,778
Funding
Provincial Gas Tax $ 41,608 $ 7,773,300  $ 7,731,692
Capital Program Reserve 555,240 2,325,900 1,770,660
City of London 816,300 2,815,400 1,999,100
City – Federal Gas Tax 7,403,000 7,403,000
ICIP – Provincial 117,924 1,025,400 907,476
ICIP – Federal 141,650 1,231,500 1,089,850
Total $ 1,672,722  $ 22,574,500  $ 20,901,778

The following programs are underway through the first ten months of the year, with narrative focusing on the year-to-date progress.

Bus replacement – Some of the peripheral equipment (cameras, AVL) has started to arrive in anticipation of the receipt of replacement buses beginning in December.

Facility upgrades – Expenditures incurred to date for hoist repairs, lighting, security cameras, painting, interior renovations, and drainage work.

Information systems & hardware – Expenditures incurred to date for the purchase of workstations and networking equipment.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and equipment.

Service fleet replacement – Expenditures incurred to date relate to the purchase of an inspector van.

Stop upgrades – Expenditures incurred to date relate to pouring of bus stop pads.

Bus stop amenities – Expenditures incurred to date relate to the purchase of bus stop lighting.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager