Staff Report #9 – Recosted 2024 Capital Budget Program

Staff Report #9

March 27, 2024

To All Commissioners

Re: Recosted 2024 Capital Budget Program

Recommendation

That the Commission APPROVE the recosted 2024 capital budget of $70,288,500 as summarized below noting the recosted budget reflects the previously approved 2024 capital budget program, program updates and carry forward amounts relating to deferred or active 2023 capital projects.

2024 Recosted Capital Budget

Description

 Source of Investment

 Total
 Capital Program Reserve  City of London Federal and Provincial  Provincial Gas Tax
Bus replacement  $ – $ 21,832,800 $ – $ 5,263,300 $ 27,096,100
Bus expansion 2,268,200 6,226,800 8,495,000
Facility upgrades 801,800 801,800
Fare processing equip. 747,500 1,747,500 2,495,000
Information systems 1,188,000  – 1,188,000
Shop & garage equip. 240,000 240,000
Service fleet replacement 155,000 155,000
Stop upgrades 100,000 100,000
Bus stop amenities 59,900 164,700 224,600
Fleet radio replacement 312,500 312,500 625,000
Smart card program  – 408,000 408,000
Highbury facility rebuild 667,500 1,832,500 2,500,000
Zero Emission Bus Pilot 12,980,000 12,980,000 25,960,000
$1,683,000 $39,670,200 $ 21,204,000 $7,731,300 $ 70,288,500

Background

At the August 30, 2023 Commission meeting, the 2024 capital budget program of $59,967,300 was approved. A recosting exercise for both capital and operating budgets occurs at the beginning of the year after all City of London funding is confirmed and takes into consideration pricing updates, program changes as well as any prior year projects that have not been completed or deferred to the future. The following table provides a summary by project of the proposed recosted capital budget.

Summary of 2024 Recosted Capital Budget

Description Original Approved Budget 2024 Program Updates 2023 Carry Forward Total
Program:
Bus replacement $ 14,918,300 $ – $ 12,177,800  $ 27,096,100
Bus expansion 8,495,000 8,495,000
Facility upgrades 500,000 301,800 801,800
Fare processing equip. 2,495,000 2,495,000
Information systems & hardware 500,000 688,000 1,188,000
Shop & garage equip. 200,000 40,000 240,000
Service fleet replacement 65,000 90,000 155,000
Stop upgrades 46,000 54,000 100,000
Bus stop amenities 224,600 224,600
Fleet radio replacement 625,000 625,000
Smart card program 408,000 408,000
ZEB fleet transition 6,783,000 (6,783,000)
Highbury facility rebuild 2,500,000 2,500,000
Zero Emission Bus Pilot 25,960,000 25,960,000
Total $ 59,967,300  $ (6,783,000) $ 17,104,200  $ 70,288,500
Funding:
Provincial Gas Tax  $ – $ – $ 7,731,300  $ 7,731,300
Capital Program Reserve 811,000 872,000 1,683,000
City of London 27,334,000 1,603,700 28,937,700
City – Federal Gas Tax 4,000,000 6,732,500 10,732,500
ICIP – Provincial 3,661,300 74,900 3,736,200
ICIP – Federal 4,398,000 89,800 4,487,800
Senior Government 12,980,000 12,980,000
Funding TBD 6,783,000 (6,783,000)
Total  $ 59,967,300 $ (6,783,000) $ 17,104,200  $ 70,288,500

2024 Program Updates

The capital budget for the 2024 Bus Replacement Program included the costs associated with the continued purchase of diesel buses. Given the City of London Strategic Objective of transitioning the bus fleet to zero-emission technology (included in the Climate Emergency Action Plan), a business case was included in the 2024-2027 multi-year budget submission to the City for the incremental costs associated with purchasing hybrid diesel/electric buses versus diesel, at an additional cost of $6,783,000. This program, referred to as ZEB Fleet Transition, was included in the August capital budget at a total cost of $6,783,000. Given the business case was not approved, the 2024 program will continue with the purchase of diesel buses and additional funds for the transition have been removed.

2023 Carry Forward

The nature and scope of capital budget projects often result in the project spanning multiple years, as such, delayed or incomplete capital projects are carried forward to the following year if still warranted. The following projects, with remaining available funding noted, are necessary for carry forward into 2024 and have been reflected in the recosted capital budget program in the report recommendation:

  • Bus Replacement ($12,177,800);
  • Facility Upgrades (301,800);
  • Fare Processing Equipment ($2,495,000);
  • Information System Software & Hardware ($688,000);
  • Shop and Garage Equipment ($40,000);
  • Service Fleet Replacement ($90,000);
  • Stop Upgrades ($54,000);
  • Bus Stop Amenities ($224,600);
  • Fleet Radio Replacement ($625,000); and
  • Smart Card Program ($408,000).

Given funds have been approved and set aside for the projects in prior years, there are no negative impacts on the current funding sources.

Bus Replacement & Bus Expansion Programs

The 2023 Bus Replacement Program experienced a delay with the arrival of 15 replacement buses arriving in early January 2024. For that reason, the bulk of the program’s budgeted costs ($12,177,800) were not incurred in 2023 and thus will carry forward to the 2024 capital budget as noted above.

At the June 28, 2023 meeting, the Commission approved the order of ten 40’ expansion buses to ensure bus availability for service expansion in 2024/2025. The program for these expansion buses was included in the 2024 capital budget at a total of $8,495,000. Arrival of the buses is expected to begin in April 2024.

With the recent approval of the 2024-2027 capital budget included in the city’s multi-year budget, administration has proceeded with an RFP for the supply of buses required for the 2024 through 2027 replacement and expansion programs. The results of the RFP and recommendation for contract award will be tabled with the Commission subsequent to the completion of the RFP process. The 2024 replacement program is budgeted at a total cost of $14,918,300 and plans for fifteen 40’ and two 60’ diesel buses.

The following table summarizes each of the 2023 Bus Replacement Program (carry forward), the 2024/2025 Bus Expansion Program and the 2024 Bus Replacement Program.

Description 23 Replacement 24 / 25 Expansion 24 Replacement
Units Amount Units Amount Units Amount
 40′ Bus 14 $ 10,965,000 10 $ 8,010,000 15 $ 12,015,000
 60′ Bus 1 1,212,800 2 2,425,600
 Ancillary Eqpmt. 485,000 477,700
 Total Cost 15 $ 12,177,800 10  $ 8,495,000 17 $ 14,918,300
Funding
 Provincial gas tax $ 5,263,300 $ –  $ –
 City of London 182,000 2,268,200 10,918,300
 Federal gas tax 6,732,500 4,000,000
 ICIP – Provincial 2,828,800
 ICIP – Federal 3,398,000
 Total Funding $ 12,177,800 $ 8,495,000  $ 14,918,300

The Commission will be provided with regular updates on the status of the programs included in 2024 capital budget.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager